Projects

Current plan


As a technical procedure a Thermolysis- Gasification process is brought to use according to the EuroTherm-Thermolysis opening method. With this procedure wood, biomass and organic waste material can and be converted into an engine fit gas. The won gas can be used as drive gas for a BHKW for electricity and warmth/cold.

Planing and establishing of a plant

The planned plant shall be built in 39291 Theeßen in Saxony-Anhalt. The property is located in a fully developed industry commercial district directly at the motorway 2.

Work step already completed


-. feasibility study of the project at the location

-. check of the promoting ability

-. application for subsidies "for the planned improvement in the regional economy structure"

-. creating of currently 16 workplaces

-. check and introduction of the plan following the federal pollution protection legal requirements

-. conclusion of the Scoping - appointment

-. unanimous positive notification of the municipality for the plan

-. economy calculation of the plan at the location

-. safeguarding of the material currents in the input area

-. safeguarding of the produced energy by buyers about gas sale

-. safeguarding of the produced energy by buyers of current over the resident network operator

-, under the specifications EEG and KWK